Optimalisasi Penjadwalan Produksi Menggunakan Metode CPM (Critical Path Method) dan Resource Leveling di PT XYZ
DOI:
https://doi.org/10.59024/jisi.v4i3.2214Keywords:
Allocation, CPM, Operator, Production Scheduling, Resource LevelingAbstract
The imbalance in operator allocation and the potential for production delays in the PM11 Emboss Machine manufacturing process at PT XYZ indicate the need for a systematic and efficient scheduling approach. Ineffective scheduling may result in workload fluctuations, uneven resource utilization, and reduced operational performance. This study aims to identify the critical production path using the Critical Path Method (CPM) and balance operator allocation through Resource Leveling. The research used production planning data consisting of 126 operations grouped into six activities. CPM analysis was conducted using POM-QM for Windows to determine the critical path and project duration, while Resource Leveling was performed using Microsoft Project to optimize operator allocation. The results showed that the optimal project duration was 139.66 hours, with the critical path consisting of Frame 1+2+Support Frame and Assy MS Emboss activities. After implementing Resource Leveling, the maximum operator requirement decreased from 17 to 10 operators, the Coefficient of Variation (CV) decreased from 58.35% to 39.10%, and the Standard Deviation decreased from 4.96 to 2.67 without extending project duration. These findings demonstrate that the integration of CPM and Resource Leveling improves scheduling efficiency and supports balanced workload distribution in the PM11 Emboss Machine production process at PT XYZ.
References
Dadang Rizaldi, M., & Singgih, M. (2024). Analisa penerapan Critical Path Method (CPM) pada proyek pembuatan crane guna memberikan penjadwalan efektif (Studi kasus: PT XYZ). Jurnal Ilmiah Wahana Pendidikan, 10(9), 418-447. https://doi.org/10.5281/zenodo.11180117
Ducas, J., Mathieu, J., Drouin, M., Sobczak, S., Abboud, J., & Descarreaux, M. (2025). The influence of workload on muscle fatigue, tissue properties, and postural stability in older and younger workers. PLOS ONE, 20(1). https://doi.org/10.1371/journal.pone.0316678
Fariham Masula, Huda, M. R. M., & Winarno, A. (2024). Literature review: Penerapan perencanaan produksi dalam meningkatkan efektivitas dan efisiensi aktivitas produksi. Jurnal Ekonomi Bisnis dan Manajemen, 2(3), 30-43. https://doi.org/10.59024/jise.v2i3.747
Gultom, P., Simamora, E., Nehe, E., Tambunan, C. H., Purba, D. Br., & Tamba, D. Br. (2025). Penerapan metode jalur kritis Critical Path Method (CPM) dengan pendekatan kegiatan dan kejadian untuk perencanaan proyek. Ekopedia: Jurnal Ilmiah Ekonomi, 1(3), 511-520. https://doi.org/10.63822/bdd4r493
Islamiyah, D., & Purnama, A. R. (2024). Strategi percepatan dan penjadwalan proyek fabrikasi peralatan ZA BIN 39D316 dengan menggunakan Critical Path Method (CPM) dan Earned Value Measurement System (EVMS). Nusantara Technology and Engineering Review (NTER), 34-38. https://doi.org/10.55732/nter.v2i1.1289
Legho, A. A. K., Kawet, R. S. S. I., & Pandeiroth, Y. C. S. (2024). Analisis kebutuhan tenaga kerja dengan menggunakan metode resource levelling. TEKNO, 22(88).
Minarosi, A. A., Dita, N., Putra, P., & Nauli, A. R. (2023). Analisa resource leveling tenaga kerja (Studi kasus: Proyek JLLB Tahap 2). MITSU: Media Informasi Teknik Sipil UNIJA, 11(1). https://doi.org/10.24929/ft.v11i1.2077
Prasisko, B., & Jumali, M. A. (2026). Identifikasi jalur kritis pada proses pemindahan sarana produksi krimer retail dengan metode CPM pada PT X. Factory: Jurnal Industri, Manajemen dan Rekayasa Sistem Industri, 4(2), 246-257. https://doi.org/10.56211/factory.v4i2.1382
Prasisti, D., & Nugroho, Y. A. (2023). Optimasi penjadwalan produksi untuk meminimalkan makespan dengan pendekatan Particle Swarm Optimization dan Genetic Algorithm. Jurnal Teknologi dan Manajemen Industri Terapan (JTMIT), 2(2), 111-118. https://doi.org/10.55826/tmit.v2i2.134
Puspitorini, I., & Bayu Adhi, S. (2024). Penerapan resource allocation dan levelling tenaga kerja pada proyek konveksi. Jurnal Minfo Polgan, 12(2), 2728-2735. https://doi.org/10.33395/jmp.v12i2.13359
Rizaldi, D. M., & Singgih, M. (2024). Analisa penerapan Critical Path Method (CPM) pada proyek pembuatan crane guna memberikan penjadwalan efektif (Studi kasus: PT XYZ). Jurnal Ilmiah Wahana Pendidikan, 10(9), 418-447. https://doi.org/10.5281/zenodo.11180117
Santoso, G., Dwi Puspita, A., & Retnowati, D. (2025). Ergonomic analysis of physical workload on work accidents and increased work productivity. Greener Journal of Environmental Management and Public Safety, 13(1), 36-39. https://doi.org/10.15580/gjemps.2025.1.032725051
Saputro, E., & Khoiroh, S. M. (2025). Evaluasi penjadwalan proyek produksi conveyor table top chain pada CV XYZ dengan pendekatan CPM. SURYA TEKNIKA, 12(1), 15-20. https://doi.org/10.37859/jst.v12i1.9337
Sebayang, S. M., & Sondakh, E. (2023). Penerapan metode CPM dalam penjadwalan produksi di PT XYZ Divisi Manufacturing Center. Jurnal Logistik Bisnis, 13(2), 8-15.
Setyowati, L., & Lasiyono, U. (2024). Optimalisasi perencanaan dan penjadwalan produksi: Kunci meningkatkan efisiensi operasional. Jurnal Inovasi Manajemen, Kewirausahaan, Bisnis dan Digital, 1(4), 50-56. https://doi.org/10.61132/jimakebidi.v1i4.354
Shabirin, M., & Putra, B. I. (2026). Workload analysis reveals excess operator capacity and incentive requirements. Indonesian Journal of Innovation Studies, 27(2). https://doi.org/10.21070/ijins.v27i2.2043
Simanjuntak, D. M., & Sari, R. A. (2024). Optimasi penjadwalan multi proyek menggunakan metode resource leveling. Jurnal Rekayasa Sistem dan Manajemen, 1, 1275-1276.
Wahyudin, C., Sukwadi, R., & Rahmawati, S. (2025). Application of project management model with Theory of Constraints to minimize project completion time and direct labor costs. Metris: Jurnal Sains dan Teknologi, 98-104. https://doi.org/10.25170/metris.v26i02.7262
Wawey, A., To'unni, L., Purwantoro, A., Aditama, S., & Uda, K. A. (2023). Optimalisasi alokasi tenaga kerja menggunakan resource leveling. https://doi.org/10.25299/saintis.2023.vol23(02).1447
Wicaksono, R. A., & Safirin, M. T. (2025). Evaluasi dan optimalisasi durasi pelaksanaan system test menggunakan metode Critical Path Method dengan software POM-QM di PT XYZ. Jurnal Serambi Engineering, X(1).
Downloads
Published
Issue
Section
License
Copyright (c) 2026 JURNAL ILMIAH TEKNIK INDUSTRI DAN INOVASI

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.








